How much housing is Seattle building?

Net new homes: units added by building permits as they reach completion (final inspection), minus units demolished. How units are counted

2024-10-06 → 2025-10-05
Net units completed, last 12 months
5,668−36%
1,510 projects

6,196 added − 528 demolished

8,906 in the 12 months before →
Net units completed, 2026 so far
3,292−39%
1,160 projects

3,707 added − 415 demolished

5,436 by the same date in 2025 →

Provisional: completions are sometimes recorded late.

Units applied for, 2026 so far
2,303−40%
818 projects
Units completed per year, by housing type
Units added by housing type above the line, units demolished below it, and the net as a line. Look for which kinds of housing drive the totals and how the mix shifts after policy changes. Click a bar to see its permits.
1,277 projects

0% of these units have a housing type inferred from the permit description because the City didn't record one; 0% couldn't be classified. How types are assigned

Trailing 12-month total
Net units completed in the 12 months up to each month. Smooths out seasonal swings, so it's the fairest way to tell whether the city is speeding up or slowing down.
Largest completions
The biggest permits completed between Oct 6, 2024 and Oct 5, 2025, and their share of the 9,440 units added in that period.
AddressTypeCompletedUnitsShare
10631 8th AVE NE
Phased project: Construction of a residential building with below grade parking and occupy per plan.
Street View
Large multifamilyNov 6, 20244094.3%
225 BROADWAY
Phased project: Construct multi-family building with below-grade parking occupy per plan. Mechanical included.
Street View
Large multifamilyApr 30, 20253453.7%
2100 QUEEN ANNE AVE N
Construct tenant improvements for a grocery store in a mixed use building per plans. Mechanical included.
Street View
Large multifamilyDec 23, 20243253.4%
2208 4TH AVE
Phased project: Construct a mixed-use high rise with residential over lower floor commercial and below grade parking occupy per plan. Mechanical is included
Street View
Large multifamilyJul 29, 20253233.4%
11201 Roosevelt WAY NE
Construct a multi-family building occupy per plans
Street View
Large multifamilyDec 17, 20242953.1%
1750 22ND AVE S
Construct a mixed-use building occupy per plans
Street View
Large multifamilyNov 19, 20242873.0%
1765 22ND AVE S
Construct a mixed-use building occupy per plans.
Street View
Large multifamilyDec 17, 20242823.0%
2245 NW 56TH ST
Phased project: Construction of a residential/retail building with below grade parking and occupy per plan
Street View
Large multifamilyFeb 6, 20252382.5%
2315 4TH AVE
Phased project: Construction of a residential and retail building and occupy per plan
Street View
Large multifamilyMay 22, 20252122.2%
2201 S GRAND ST
Establish use as multi-family restaurant and office building construct mixed-use building and occupy per plans.
Street View
Large multifamilyDec 27, 20242062.2%
All permits adding units in this period →